TERM OF REFERENCE
Review of
the Integrated Water Supply, Sanitation, and Hygiene
Promotion Project in Keerom, Papua
Indonesia
(Project 08-114-0002-3)
- Summary
Title
|
Review of the Intergrated Water Supply, Snitation and Hygiene Promotion
|
Duration
|
The period covering the watsan-CBHFA programme/activies starts in 2011 en ends March 2015
|
Location
|
Papua, Indonesia :
In Keerom District, Arso Timur Sub-district; Wonoredjo
village, Suskun village and Yetti Village
|
Partners
|
The programme has
been implemented by the Indonesian Red Cross (PMI) with the financial and
technical support of the Netherlands Red Cross (NLRC).
|
Purpose of evaluation
|
The
primary purpose of this evaluation is to review the project from its
initiation until its finalization in order to learn from the complexities of the project and to use the experience
in Keerom for future interventions. The review
will be used as a resource for a “lessons learned workshop” for all
stakeholders (PMI staff, PMI Chapter/Branch Governance, PMI HQ and NLRC).
|
Request for quotation
|
The quotation (in English) should be sent to the
Netherlands Red Cross, Ms. Kartika Juwita (email: KartikaJ@redcross.nl ). This contact can also be used
to request for more information.
The quotation should include:
-
Track record of earlier evaluations and Curriculum Vitae
-
Draft
work plan;
-
Budget, including daily professional fee (incl. tax, which is
considered the sole responsibility of the Evaluator) and total of days
charged, other costs (if needed), such as translation costs.
The deadline for submitting the quotation
is: ? April 2015
Quotations will be assessed on price and quality
(i.e. proposal, experience evaluator; workplan).
The evaluation is expected to take
place in third week of April , and could start by the 20th of April 2015. The final
report should be submitted before 30h of April 2015.
|
2.
Background
The
Netherlands Red Cross (NLRC) has supported Palang Merah Indonesia (PMI) for the
implementation of integration Water, Sanitation with hygiene promotion component projects for many years in
Indonesia. Over the last years, the software aspect has become more and more
important in the delivery of a coherent approach in this project. The NLRC and
PMI realise a holistic approach of software and hardware is desired, placing
more emphasis on community organisation- and hygiene promotion aspects.
The PMI
Watsan programme in Papua was initiated in 2010 to start in three villages
in Keerom district Papua (Wonoredjo, Suskun and Yetty). A proposal was presented in June 2011 with the planning for a two stage of project implementation. As the implementation of the first phase of the
project took much longer than projected, the second phase of the project could
not be materialized.
The
stages of the project:
The assessment was
done in August 2010. The first stage of the implementation project started on 1
May 2011 with the ending scheduled for 31 August 2013. The project was divided
into four stages:
·
The first stage being
the assessment and proposal writing initiated from May – December 2012
·
The second stage is
the preparation and initiation and takes place from January 2012 – July 2012. Main activities are;
Preparation and
negotiation of a Memorandum of Understanding (MOU) to be signed by PMI and
NLRC,
Staff recruitment to
manage the project in Papua
Baseline survey
Project socialization and
M&E as well as
reporting tool in place.
·
The third stage is the Project Delivery that was
assumed to take 12 months from from August 2012 – July 2013. In this third
stage PMI and community volunteers are recruited and trained on CBHFA:
Volunteers carry out hygiene promotion
Water and sanitation
facilities are built
Midterm evaluation is carried out
Networking and
Acquisition activities are carried out at all levels with stakeholders
·
The fourth phase will be carried out
simultaneously with the activities of the third stage, in the last two months
of the third stage ( July and August 2013)
Project evaluation
Sustainability planning
Project preparation
for the second phase Project closure
reporting
The
first strategy of the program is “Community development”, and includes
activities that improve the health conditions in the village partners, by
providing basic health services. This includes the introduction of trained Village
Health Volunteer’s who provide first aid and disseminate on health and hygiene
measures. Finally, in three Villages clean water
systems and latrines constructed through participatory approach (PHAST). The
combination of providing clean water, sanitation and health facilities and
awareness raising of the community, will improve the health situation in this
area: it is expected that common and water borne diseases will reduce in those
villages where all project activities implemented.
The
second strategy is “PMI Capacity Building”. Being the project-holder and thus
the main coordinator and implementer gives PMI the chance to profit from the
project in terms of experience and strengthening of branches, in order to
reduce the distance between the branches and the beneficiaries. This project is first development project implemented in
Papua, previously they were implemented activities based on requests.
3. Scope
This review
is mainly aiming at appraising the challanges faced when implementing the project and impact it had
on the communities and on PMI. The main focus of the review is to understand what happened within
the project period in terms of initiatives, decision making, implementation
activities, internal and external guidance/support, communication, capacity
building etc. This should be related to the final outcomes and its effect on
the communities. The review may also assess the expectations of the different
stakeholders and whether these could be met. The review will be a major source
for a lessons learned workshop. The workshop will involve all stake holders and
will aim at improve the capacity of the Chapter and Branch to attract and
implement comparable projects.
Considering
the fact that to a large extent baseline data are not available, much emphasis
will be on methodology of the evaluation.
The review should take into account the external and internal environment, as well as the political situation, culture, goverment and other stake holders intervention in the selected communities.
The review will take place in the communities of Keerom, Jayapura and Jakarta.
4. Key
questions
Key questions include, but are not limited to:
Appropriateness
- Was the intervention appropriate according to the perception (expressed needs/demand) of the target population and/or according to national policies: how were power relations, cultural perceptions and relevant customs of beneficiaries assessed, and taken into account?
- At
the time of project implementation, were the approaches and technologies
selected most appropriate for the specific context?
Moments
·
How did the
project develop over time. On a time line; when and where were decisions made,
initiatives taken, events organised, field visits, etc. which had impact on the
progress of the implementation of the project.
·
What are the main
factors which influenced positively or negatively the progress of the project.
Outcomes
and Impact
·
To which extent were the overall objectives
achieved?
·
Did the project have any unforeseen harmful
impact?
·
What can be assumed to be the major factors
that contributed to the impact on the health and care for the beneficiaries?
·
How sustainable are the interventions?
PMI Organizational Capacity and Development
·
Did NLRC, PMI NHQ Management and the PMI Chapter/Branch level in Papua have a common understanding of the project design and implementation? In particular also on the capacity building.
·
How did PMI HQ and Branches assess the required capacity and
ensured the establish the capacity before the start of the project? How was
capacity building included in the project? Was this sufficient?
Replicability
- Has there been a degree of replication within or beyond the project area by the National Society?
- What can be done to strengthen the process in order to ensure it is sustained and duplicated beyond the project area?
5.
Methodology
The methodology will at least include the following
elements:
- The evaluator will use observations and study
reports and other relevant documents to collect data. All available written
documentation will be provided.
- Both quantitative and qualitative information is to
be used. However, emphasis will be on qualitative
data and analysis.
- Main method for data gathering will be interviews.
To ensure openness to unexpected results or side effects and deal with cultural
sensitivities, the evaluator needs to be from Papua or hire his own indigenous
translator when holding interviews in Papua.
- Main stakeholder’s perspectives, should be taken
into account. The main stakeholders can be categorized as beneficiaries, PMI
volunteers, PMI Branch staff, PMI Branch Governors, PMI Chapter staff, PMI
Chapter Governors, NHQ staff, NLRC staff and Indonesia Government
Institutions.
The review requires
evaluators to familiarise themselves thoroughly with characteristics of the Red
Cross and Red Crescent Societies movement; it’s principles, limitations and
associated dilemmas and limitations.
6. Outputs
Output
|
Deadline
|
|
1.
|
Collection of
essential data required for the evaluation and a schedule for interviews and field visit.
|
Before 23 April 2015
|
2.
|
A draft synthesis report, covering findings,
conclusions, not exceeding 25 pages (excluding annexes and a summary of 1
page). This report includes conclusions and recommendations.
The report will
include detailed analysis of the situation, findings, conclusions and
recommendations
|
Before
30 April 2015
|
3.
|
A final synthesis report, covering findings,
conclusions, not exceeding 25 pages (excluding annexes and a summary of 1
page). This report includes conclusions and recommendations.
|
|
5.
|
Participate in a lessons learned workshop
|
Before 8 May 2015
|
7.
Responsibilities and lines of communication
Implement review
|
Consultant
|
Submit report to
|
PMI
NHQ, health division and planning bureau
NRLC
Jakarta office
|
The
evaluator will be briefed at PMI NHQ and NLRC programme office related to Purpose
of evaluation; expected results; context; reporting & finance
8.
Profile of the evaluator(s)
·
Strong methodological background
·
Background in social and antropology studies
·
Experience in conducting impact evaluations
·
Demonstrated fluency in English and ability
to write concise and comprehensive reports
·
Cultural sensitivity and excellent
interpersonal skills
·
Computer literate
·
Experience in watsan and CBHFA preferred.
·
Experience in conducting reasearch and working in eastern
part of Indonesia and Papua specifically preferred
·
Must have good knowledge of the Red Cross
fundamental principles, Code of Conduct and various ways of collaboration
between the different segments of the RCRC movement.
8. Responsibilities
and Tasks:
·
The consultant will be responsible to develop an evaluation proposal that
depicts the research methodology, detailed work plan and proposed budget
including consultancy fee, logistical arrangements and support to the
consulting services (translator)
·
The consultant will be responsible to deliver consulting services in
accordance with agreed evaluation proposal and at the end produce a
comprehensive and high quality final review report
·
The consultant will, in cooperation with the provider of the assignment,
make arrangement for the field visits and shall cover the cost all logistic
required to support field activities
·
The consultant is expected to share a draft report prior to developing
the final report. The final evaluation report shall be submitted on time as per
agreed schedule (Bilingual in English and Bahasa Indonesia)
10.
Planning
Preparation
|
2 days
|
Desk Review
|
3 days
|
Field visit Papua
|
6 days
|
Interviews Jakarta
|
5 days
|
Report writing
|
3 days
|
Debriefing
|
1 day
|
Final report
|
1 day
|
The
assignment is has a maximum of 21 working days and should be finalized in 4
weeks time .
11. Reporting
The draft report
will be assessed by the assignment provider before delivering the final report.
The comments will be taken up (or commented on) in the report. The report will be in English and Bahasa
Indonesia and contain a brief introduction and description of the methodology,
constraints in implementation, a comprehensive analysis section and a section
on findings and recommendations.
12. Ownership of data
All
data collected during the evaluation will be handed over to and become property
of the NLRC. Evaluators must therefore treat findings in a confidential manner
and require advance written approval from the NLRC for sharing any information
with third parties, in whichever form.
No comments:
Post a Comment